EDF: new delay and a soaring cost for the Hinkley Point reactors

Endless.

EDF: new delay and a soaring cost for the Hinkley Point reactors

Endless. The French energy group EDF announced on Thursday that the construction site of two new generation nuclear reactors (EPR) at Hinkley Point in England would be delayed by another year and additional costs of at least 3 billion pounds. . "The start of the electricity production of Unit 1 is now scheduled for June 2027. The risk of postponing the delivery of the two units is assessed at 15 months, assuming the absence of a new pandemic and additional effect of the war in Ukraine," the group said in a statement.

Initially, the start-up was planned for the end of 2025, and it had already been postponed, last year, to June 2026. The plant is located in Somerset (south-west of England). EDF now estimates the cost of the project to be "between £25 and £26 billion" in 2015, up from £18 billion in 2016, when the UK government gave the green light and construction began.

The delay is blamed on the two-year pandemic: “people, resources and the supply chain have been stretched and their effectiveness has been limited. In addition, the volume of studies and civil engineering works, and the cost of these works and in particular of the maritime works, have increased”, explains the group. The next milestone will be the installation of the dome on unit 1 of the plant, in the second quarter of 2023, compared to the end of 2022 previously.

EDF accumulates bad news

The project, originally controversial and contested by French unions for its cost, had already been reassessed between 22 and 23 billion pounds. It did not escape the setbacks suffered by other EPRs. The EPR (European Pressurized Reactor) is a model of nuclear reactor that is more powerful and designed to be safer than previous generations. Three are complete, in Finland and China, and three are under construction, one in France and two at Hinkley Point.

Read alsoAfter the radioactive leaks from an EPR reactor in China, EDF wants to be reassuring

But the Finnish reactor (Olkiluoto-3) started in March 12 years late, and of the two Chinese EPRs commissioned in 2018 and 2019, one has been shut down since July 2021 for technical problems. As for the French reactor, in Flamanville, the cumulative delays reach 11 years for fuel loading now scheduled for the 2nd quarter of 2023, and the cost has risen to 12.7 billion euros according to EDF's estimate as of January 12, 2022 In 2006, this very powerful 1650 MW reactor was announced at 3.3 billion euros.

EDF has been accumulating bad news since the beginning of the year. The group had to be recapitalized in April, and its profit will plunge this year in large part because the French state has asked it to sell more electricity at low prices - a file on which the CEO is publicly opposed to the government.

The nuclear challenge

In addition to the delays of the French and English EPRs, the group must also solve a pipe corrosion problem which forced it to shut down 12 of its 56 French reactors. In total, more than half of the reactors in France are now shut down for maintenance. Hinkley Point C is the only nuclear power station being built in the UK. EDF is the project owner, while its Chinese partner CGN owns a third of the project. It adjoins the Hinkley Point B nuclear power plant, commissioned in 1976 and which EDF has planned to shut down by July 2022.

The ambition across the Channel is to maintain the nuclear share of the energy mix at 20% in order to achieve carbon neutrality by 2050 - while there are currently 15 reactors in the United Kingdom on 8 sites. London wants to produce 95% low-carbon electricity by 2030. In France, EPR technology remains at the heart of the energy strategy. President Emmanuel Macron has announced his intention to relaunch a nuclear program with six new generation EPR2 reactors, praising in particular the climate advantage of the electricity thus produced.

This long-term project will not be completed during the five-year term. The first commissioning is not expected before 2035 or 2037. But the financial stakes are immediate and considerable, with an estimated cost of more than 50 billion euros for six reactors.


9

NEXT NEWS